FG Cracks Down on Unapproved Contract Variations in MDAs
FG Cracks Down on Unapproved Contract Variations in MDAs
The Federal Government, through the Bureau of Public Procurement (BPP), has barred Ministries, Departments, and Agencies (MDAs) from processing upward revisions of contract sums without obtaining prior approval and certification from the Bureau.
The directive was contained in a statement issued on Sunday and signed by the Bureau’s Head of Press and Public Relations, Zira Nagga.
According to the statement, the new policy introduces sweeping reforms that centralise the review of all contract variations and scope modifications under the supervision of the BPP, in a bid to curb cost inflation and corruption in public procurement.
The guidelines, issued under Sections 5(a) and (o) of the Public Procurement Act 2007, implement a Federal Executive Council-approved policy communicated through the Secretary to the Government of the Federation in December 2025.
Titled “Contract Variations: BPP Releases Guidelines,” the new framework replaces the 2013 rule which required Presidential approval only for variations above 15 per cent of contract value or N1 billion.
Under the revised policy, all requests for variation orders, fluctuation claims, or scope modifications—regardless of value—must now first be submitted to the BPP for review and certification before any further approval is granted.
The Bureau stated that a Certificate of No Objection, valid for six months, will now be a mandatory requirement before any variation can proceed. It warned that non-compliance will attract sanctions under the Public Procurement Act, including suspension of responsible officers and possible debarment of contractors.
BPP Director-General, Adebowale Adedokun, said the reforms are intended to block loopholes that allow cost inflation and misuse of public funds.
“Variations must not become a backdoor for cost inflation and scope creep,” he said, adding that all adjustments must be “necessary, justified, and deliver value to Nigerians.”
The guidelines further distinguish between permissible and impermissible grounds for contract variation. Acceptable reasons include unforeseen site conditions, design errors, statutory changes after contract award, major economic shocks, force majeure events, and value engineering improvements that reduce cost without altering project scope.
Related stories
News
CBN Holds Benchmark Interest Rate at 26.5% for Second Straight Meeting Amid Global Uncertainty
The Central Bank of Nigeria's Monetary Policy Committee has retained the MPR at 26.5% following its 306th meeting, maintaining a tight policy stance despite slightly easing inflation and citing risks from renewed Middle East tensions.
News
FG to Return 13 Unbid Oil Blocks to Licensing Pool After 2025 Round Draws 143 Firms
NUPRC says 13 of the 50 oil and gas blocks offered in the 2025 Licensing Round failed to attract bids and will return to the national licensing basket, even as 143 firms submitted about 200 bids for the remaining assets.
News
Gov AbdulRazaq Thanks Tinubu as New Army Battalion Heads to Kwara to Tackle Banditry
Kwara State Governor AbdulRahman AbdulRazaq has praised President Tinubu for approving a new army battalion for Omu-Aran, saying the move will boost the fight against banditry and kidnapping in the state.
News
Tinubu Approves 2026 Oil Licensing Round, Offers Fresh Hope to Unsuccessful Bidders in Ongoing Exercise
President Tinubu has greenlit Nigeria's third consecutive oil licensing round for 2026, giving investors who miss out on the current 2025 bid exercise another shot at securing upstream petroleum assets.
Comments (0)
Leave a comment
All comments are moderated before publishing. Your email is never published.